The Newcold planning application is now been shown, the building which has been built at Newmarket has not activated the Stadium clause.
So now an update on what has being going on...
Conditional offer: Construction of a 8000 capacity stadium
Main stand 3000 seats and all offices, changing rooms, and corporate...Popular stand with 5000 capacity
Car parking
And to be ready for start of 2017 season, but we are no further forward with this.
So what next?
Action can't be taken until next application comes forward to Newmarket site
Council have a choice - either recommend approval or reject it
Rejected - planning inspectorate will take over
Approved - high court judicial review
We may now have to take to court...estimated costs at 50k
Belle Vue costs 250k to play at each year
The money could be better used into the first team, a new facility would give us a better income. A better first team.
As a city we need Wakefield Trinity Wildcats