Ive had it confirmed, that my suspicions in an earlier post re Planning conditions not being met, are infact true.
There are something like 74 conditions that need to be fulfilled as part of planning approval.
As a result we wont see any stadium being built until the developers get round to satisfying all these conditions.
Examples of submissions required by planning include
Handling of soil resources
Waste management plan
Energy efficiency
Conservation management plan re the bottle shop
Disposal of foul water
Surface water regulation
Relocation of newts
Presence of badgers on site
Eradication of Japanese Knotweed
Tree protection plan
landscaping and planting plan
Closure of access points to site
Car parking contingency plan
Plan for emergency access link
Management of Tesco service yard
Matchday crowd movement plan during store trading hours
Widening of footway at Peasley cross lane
Highway improvement scheme on Linkway East
Construction of site access points
Detailed land stability study
Human health and environment risk assessment
Samples of construction materials
remediation strategy
project risk register