Re: Stadium Site pictures : Wed Mar 03, 2010 10:27 pm
The Doghead wrote:
According to the St Helens Reporter, A Judicial planning review lasting 12 weeks has been given as the reason why the club has not held the fans forums.
The forums were put back because the review period does not end till the 15th of March, the club does not expect any problems with the findings of the review.
The forums were put back because the review period does not end till the 15th of March, the club does not expect any problems with the findings of the review.
There is not an actual review on-going. If there was you would / could have serious problems.
It is actually the period (3 months) where-upon a third party can raise a challenge to a planning consent under the Civil Procedure Rules part 54. The challenge has to be made against the process used to grant the planning (eg the right parties weren't consulted, etc) and not whether planning should have been granted or not.
Whilst I can understand not starting the works on site whilst the risk remains (although standard practise is for the Client to retain the risk and as Langtree / Saints / the Council got the planning rather than a contractor you would expect this to be the position here and for works to have started) I cannot for the life of me see why this would affect presentations to fans.
I would guess more likely is that final negotiations are on-going with the "preferred" contractor to wring the last bit of fat from the price and to negotiate away any clarifications that might have been part of the tenders submitted.
Are the works Birse have started on required to ve complete prior to commencement of the main building project (for access to the works)?
As for "small drill on-site" very un-likely to be a piling rig as you would have had the installation of a piling mat first. More likely to be ground investigations required to discharge one of the pre-start planning conditions. I would guess you'd be looking at about 3 to 4 weeks for the report to be issued and then another week or two to produce and negotiate/agree the report required by the planners for condition discharge before groundworks can start on-site.