Going to post this here because I am trying hard to keep away from the mud-slinging and these are genuine questions.
I know some of your posters will know the answers to these questions.
Are you submitting a reserved matters application for GH or is it going to be a full planning application because the original permission lacked sufficent detail at outline and/or stadium designs have sufficiently changed to require a full application?
Either way, getting planning permission is a formality, but obviously if it can be dealt with under delegated powers under a reserved matters application it will be much quicker!
So, if a reserved matters application then you are looking at end of Feb for planning and if full, and therefore it goes before the committee, end of March/April would be more likely would you think?
So earliest start on site would be March/April and maybe June/July, so is the best possible plan to get the contracts signed before your SL application goes in? What is the club line on start and completion... or are they keeping it quiet?
Actually, better questions, what is the projected build programme from start to occupation?